The Works

The complex conversion of a nightclub into a bank, in a shopping centre in central Middlesborough.

As well as the challenge of finding High-Alumina Cement (HAC) concrete within the structure, works included the creation of new openings for the banks facade, and the creation of new floor voids to accommodate new staircases. We increased the floor capacity to accommodate the weight of safes, in -filled existing stairs and floor voids, and refurbished part of the basement in order to house a new substation.

The basement had previous high water tables, causing constant flooding, so new sumps and tanking systems had to be installed.

Looking For Your Next Engineering Partner?

We work across all sectors and provide the kind of expertise built from experience.

If you are looking for an engineering partner you can lean on, and trust, to deliver the best in value solutions, talk to us.

Get In Touch

Sign Up To Our On Reflection Newsletter

Thank you for subscribing.